Included with duct mount
Qty Description
1 Duct Mount Base White with #4-40 x ½” mounting studs
1 Clear Cover
2 Air Sampling Noses, mounted with adhesive
1 RF cable extender with SMA connectors, 16.5cm length with cover seal
1 Power wire grommet
1 Straight Antenna for WellStat Air Quality Monitor
2 #4-40 Hex Nut, for mounting WAQ Mounting Plate to Duct Mount Base
4 #4 x ⅜” Plastite Screws for mounting clear cover to Duct Mount Base
4 #6 Self-tapping and self-drilling screws for mounting base to sheet metal duct
Optional Features
For use with liquid-tight conduit fittings use WAQ-CN38 silicone bushing set, compatible with McMaster 9106K41.
If gas-tight seal is required between the base and the duct use 2 each of McMaster 2418T143
To extend air sampling nose up to 12” into the duct use WAQ-ALTB, cut to length. (not shown)
Use mounting template WAQ-DCTMNT for proper location of holes for air sampling holes.
Mounting Procedure
1. Identify Ideal Location
Keep close to power source to limit electrical run if possible.
Locate in clean return or supply stream // avoid mixing plenum for best results.
Allow for enough space to remove cover and service WAQ.
2. Start with template. There will be one (1) delivered per building with duct mounts.
Drill self-tapping screws into (4) corners. Locations match actual duct mount.
Drill pilot hole for duct penetration. Use a 1/8” drill bit. Steel bushings are inlaid into template, there is no risk of damaging template.
3. Bore out duct penetration hole. Using a step bit is recommended.
Step slowly
Drill hole down to 7/8" OD
4. Slide duct mount in through holes. Make sure that inserts have
5. From inside, install scoops.
6. Mount in WAQ with back-plate installed.
7. Connect antenna
8. Power
In MERs Chief Engineers may require electrical runs kept in conduit/liquid-tight.
Drill ½” or ¾” holes into bottom of duct mount enclosure to fit gland connections.
Can use BX cable OR liquid-tight [liquid-tight recommended].
Fastener Detail